Barcelona have reached an agreement with Turkish construction company Limak to oversee the final phase of the Spotify Camp Nou redevelopment, bringing greater certainty to the long-running renovation project.

The agreement confirms that Limak will remain responsible for completing the stadium, with both parties reaching an understanding over the remaining construction work after months of negotiations.

According to Mundo Deportivo, the deal has been signed following confirmation that investors have deposited an additional €300 million into the project, with the increased financing approved by Barcelona members at the club's Ordinary General Assembly on September 19.

One of the most significant stages still to come is the installation of the stadium roof, which will involve the lifting of a 3,000-tonne structure known as the 'Big Lift'.

Limak retained for final stage of Camp Nou redevelopment

Barcelona had previously considered appointing another construction company if disagreements with Limak over deadlines and the execution of the project could not be resolved.

However, an agreement has now been reached, meaning the Turkish company will see the redevelopment through to completion.

Limak will continue to use subcontractors during the final phase, as it has done throughout the project, while the newly agreed arrangements broadly maintain the terms of the original contract.

The additional financing has also provided further support for the redevelopment. Barcelona's members approved €510 million in extra funding, including €300 million for stadium construction and a further €210 million through media notes to help manage cash-flow pressures.

The club completed the €300 million financing operation on November 13, clearing an important hurdle ahead of the remaining construction work.

Big Lift timetable provides clarity over Barcelona return

The installation of the roof is expected to begin immediately after the conclusion of the current season, although an exact start date has not yet been confirmed.

Under the agreement, the Big Lift must be completed during the second half of the 2027-28 campaign.

Its completion will allow Barcelona to reopen the stadium with all three tiers available to supporters, including the previously unfinished Third Tier.

The club has provisionally reserved the Estadi Olímpic Lluís Companys for the first half of the 2027-28 season as a precaution, but the current expectation is to return to Spotify Camp Nou during the second half of the campaign.

Barcelona had already ruled out reopening the Third Tier in stages, with the approach presenting difficulties around evacuation arrangements and obtaining the necessary municipal licences. Instead, the entire section is expected to open when the team returns.

New facilities expected to boost Barcelona revenue

The stadium's commercial performance has helped reassure investors about the financial potential of the redevelopment.

Spotify Camp Nou is currently generating significant income despite operating with a reduced capacity. The latest league meeting with Real Madrid brought in €19.1 million in revenue, with 62,055 supporters in attendance.

However, further growth is expected from the completion of the new facilities, particularly the expanded Barça Store and the club's museum.

Both are currently undergoing their final interior works and are expected to become operational in early 2027, providing additional commercial opportunities beyond matchday ticket sales.

The double tier of VIP boxes is another major part of Barcelona's plans, although the facilities are not expected to be fully operational until the 2028-29 season.

That campaign will also see Spotify Camp Nou host the Champions League final, 30 years after the stadium last staged the showpiece in 1999, when Manchester United defeated Bayern Munich.

With Limak now committed to the final construction phase and the additional financing secured, Barcelona have taken an important step towards completing one of the most significant projects in the club's recent history.